Day To Day Work at Site

Time-Line : 1st Feb. 2016 - St. Regis Langkawi work site.
Creation of bunds to make access-way to centre of Lagoon.
Time-Line : 7th February 2016 - St. Regis Langkawi work site.
Installation of geotube for breakwater construction.
Time-Line : 22nd Feb. 2016 - St. Regis Langkawi work site.
Geotextile were sewn together and laid along the beach at low tide.
Time-Line : 27th Feb. 2016 - St. Regis Langkawi work site.
Laying of armour rocks for breakwater during night work.
Time-Line : 13th April. 2016 - St. Regis Langkawi work site.
In a "Pelican" 3 in 1 Conveyor vessel loaded with sea-sand berthing at St. Regis Langkawi anchorage.
Time-Line : 13th April. 2016 - St. Regis Langkawi work site.
Laying of armour rocks on and along the geotube.
Time-Line : 8th May 2016 - St. Regis Langkawi work site.
On-going rock laying as well as shifting of sea-sand works.
Time-Line : 19th May 2016 - St. Regis Langkawi work site.
Inspection of works at site by INR team.
Time-Line : 20th May 2016 - St. Regis Langkawi work site.
Visit to man-made Daisa Island.
Time-Line : 26th May 2016 - St. Regis Langkawi work site.
Preparation for the Grand Opening of St. Regis Langkawi.
Time-Line : 26th May 2016 - St. Regis Langkawi work site.

There is no video clip yet

Amphibian excavator sand-pump working beside VVIP Villa sucking slurries out.

Latest comments

12.09 | 22:23

Hi sir, mikarataruia@gmail.com, would like to communicate on Sand self unload ships, at least 2 vessels for hire mode, landfill, 80 km distance, 6 months, 24 hr

18.08 | 02:00

If your as supply cif marine sand to Mao Phillipine...
Please reply asap

24.05 | 03:26

Email: tony.sze@indopac-resources.com

23.05 | 06:47

HK-based company seeking the sand loading platform of your project. Sand concession in the NE Luzon of the Philippines. Target production: 300,000MT/mth.